The Independent Electricity System Operator (IESO) continues to update and revise its Long-Term 2 Request for Proposals (LT2), which aims to procure new build electricity generation facilities larger than 1MW to meet Ontario’s long-term energy needs, and new build electricity generation and storage resources greater than 1MW to meet long term capacity needs. During a stakeholder engagement presentation on December 12, 2024 pertaining to the LT2, IESO provided updates that prospective proponents should be aware of. These updates include forthcoming substantive changes to procurement materials, as well visibility with respect to procurement milestones and timing. The highlights from the stakeholder engagement session are summarized as follows.
The IESO released the key milestones for Window 1 (for projects with a commercial operation date (COD) of May 1, 2030). The milestones (while still subject to change) are as follows:
Milestone |
LT2(e) |
LT2(c) |
Final documents release |
February 27, 2025 |
February 27, 2025 |
Deadline for questions and comments |
April 24, 2025 |
June 26, 2025 |
IESO’s deadline for issuing addenda |
May 8, 2025 |
July 10, 2025 |
Registration deadline |
June 19, 2025 |
August 21, 2025 |
Proposal submission deadline |
July 24, 2025 |
September 25, 2025 |
Target date for notification to selected proponents |
January 20, 2026 |
March 24, 2026 |
The IESO also explained its “Windows” approach, stating that each window in both streams is a “separate/standalone procurement”. That said, the number of windows, targets and dates are subject to change. The current procurement windows and targets for the LT2 energy stream are as follows:
Window No. |
COD |
Energy Target |
Capacity Target |
Window 1 |
May 1, 2030 | 3 Twh | 600 MW |
Window 2 | May 1, 2031 | 1-3 Twh | 400 MW |
Window 3 | May 1, 2032 | 2-4 Twh | 300 MW |
Window 4 | May 1, 2033 | 2-4 Twh | 300 MW |
In late November, the IESO received a directive from the Ministry of Energy and Electrification to launch the LT2 RFP, outlining general policy considerations driving the procurement. Additionally, the totality of the procurement under the LT2 RFP (for all submission windows) will target the acquisition of:
We note that on December 11, 2024, the provincial government requested that the IESO expand its overall procurement targets from 5,000 MW to 7,500 MW and report back on options to run two additional procurements alongside the LT2 procurement, including:
Proponents can expect the following key developments and changes to the forthcoming revised procurement materials:
Further to the previous draft LT2 documents that were issued on November 22, 2024, the IESO is expected to release a next set of documents toward the end of the week of December 16, 2024. The IESO has indicated that these documents will be substantially similar to the final versions because all outstanding policy issues have been resolved. Written feedback on presented materials and forthcoming draft RFP and documents will be due on January 10, 2025. Additionally, the IESO will host an engagement session in late January before releasing final documents in February 2025. Given these developments, interested participants must ensure they are prepared accordingly with their proposals, and provide any comments or questions to the IESO prior to the LT2 RFP’s release next year.
To discuss these issues, please contact the author(s).
This publication is a general discussion of certain legal and related developments and should not be relied upon as legal advice. If you require legal advice, we would be pleased to discuss the issues in this publication with you, in the context of your particular circumstances.
For permission to republish this or any other publication, contact Janelle Weed.
© 2024 by Torys LLP.
All rights reserved.